Worked example: renovating a Gründerzeit flat in the right order

altbau.com editorial · Updated: November 2026 · 4 min read
A period building before work begins — the sequence matters more than the individual product. Photo: Pexels (royalty-free)

What this example is about

Picture a flat in a Gründerzeit building from shortly after 1900: three tall rooms, wooden floorboards, box-type sash windows, a gas combi boiler fitted later, and wiring accumulated over several decades. The flat is habitable but has not been fundamentally updated for a long time. This constellation is typical of the questions we receive — and it is why the sequence of work matters more than the choice of individual products.

This is a composite worked example, not a documented building site and not a quote. It deliberately contains no prices, durations or floor areas. It shows which questions have to be asked in which order to turn a wish list into a workable plan. Only the order of thinking transfers to a real building, not the outcome.

Step one: record the existing condition before opening anything up

Before any trade is commissioned, come the documents and a slow walk-through: the building file, the declaration of division, owners' meeting minutes, the energy certificate, invoices from earlier work and, where relevant, the monument register. The cellar, attic and stairwell are part of it, not just the flat. Damp plinths, cracks around reveals and later surface-run cables say more than a freshly painted room.

In our example this reveals a local preservation statute. That changes the plan immediately: replacing the sash windows is no longer only a cost question but a permission question. Had this surfaced after the order was placed, the damage would have outweighed any benefit of a quick start.

Step two: safety and causes before finishes

The old wiring comes before the floor. Not because it is visible, but because new cables would later open up walls and ceilings that had just been finished. A qualified electrician checks which circuits exist, whether an earth conductor reaches the sockets and where residual-current protection is missing. Only then can the useful positions for additional sockets be decided.

The moisture question runs in parallel. In this scenario one external corner of the bedroom is slightly damp in winter, with no salt marks and no smell. That points more towards condensation on a cold wall surface than towards rising damp — but it is a working hypothesis, not a diagnosis. Before any insulation, filling or paint, it needs to be observed over several weeks and accompanied by measurement.

Step three: think of components as a sequence

The survey produces a table rather than a shopping list. Each component gets three columns: what has to be settled first, what triggers a legal or technical check, and what a later measure would destroy again. That sounds bureaucratic, but it prevents the classic mistake of paying for the same wall twice.

Step four: coordinate boards, windows and heating

The floorboards are sanded only once no further cables have to run beneath them and the moisture question is settled. Before that, the remaining wood above the tongue and the position of nail heads are checked; loose boards are refixed before the machine arrives. The finish follows use, not the catalogue: open-pore oil allows local repairs, lacquer is more closed but harder to touch up in one spot.

The window decision follows from the statute and from the condition of the reveals. In our example, overhaul with new seals and improved glazing preserves the appearance, while a full profile replacement would need permission. The radiators stay, but are bled and the system is hydraulically balanced by a contractor — a measure often missing from plans because it produces no visible new component.

What this example does not do

It gives no amounts, because region, condition and preparatory work shift every quote. It does not claim the sequence is the same for every building: a listed stairwell, underfloor heating in the screed or suspected dry rot would change it. And it does not replace an inspection on site.

Anyone working through the same situation with real documents will find the questions in the viewing checklist, the vocabulary in the glossary and the legal triggers in the measure matrix. The pages are intended in exactly that order: check first, then classify, then plan.

Planning work on an old building?

Windows, wiring, heating, floors — model every line item before you get quotes.

Open the calculator

For orientation only — requirements depend on the building, the state and the lease. No legal, tax or energy advice. Questions for the editors: hello@altbau.com